Premier Turfing returned to Effingham Golf Club in Surrey during summer 2026. They completed the second phase of an ongoing greens drainage programme.

Following the successful completion of the first phase, the club appointed Premier Turfing to continue improving drainage performance across a further group of putting surfaces. The latest phase was designed to improve water movement through the soil profile. In addition, it supports healthier turf and helps create firmer, more consistent greens throughout the year.

Phase Two of the Greens Drainage Programme

Preparation for the second phase began well in advance of the works. Drainage pipe, sand and gravel were delivered to site ahead of the team’s arrival. This allowed installation to begin efficiently once mobilisation was complete.

The works were programmed for August 2026 and formed a continuation of the drainage improvements already completed during the first phase.

As before, the emphasis was on carrying out the installation accurately while keeping disruption to the established putting surfaces to a minimum.

Greens Drainage Installed at 2 Metre Centres

At Effingham, the drainage laterals were installed at 2 metre centres. This provided close spacing across the greens to improve the movement of excess water through the soil profile.

This type of closely spaced drainage layout is particularly effective on golf greens, where surface firmness, consistency and recovery after rainfall are especially important.

Premier Turfing’s specialist greens drainage equipment allows narrow trenches to be installed efficiently across sensitive turf areas. Once the pipework was in place, the trenches were backfilled with suitable drainage materials before the surfaces were carefully reinstated.

Careful Installation on Established Putting Surfaces

Drainage work on established golf greens requires a different approach from larger-scale land drainage.

Accuracy, cleanliness and careful reinstatement are essential if the putting surfaces are to recover quickly. Therefore, the team worked methodically through the programme. They combined specialist machinery with detailed hand finishing where required.

This approach helps ensure the trenches remain clean, the drainage materials are installed correctly and the finished surface is left in the best possible condition for the greenkeeping team to manage through recovery.

The project was expected to take approximately four to five weeks, subject to site and weather conditions.

Improving Long-Term Green Performance

Effective greens drainage can make a significant difference to both turf health and playability.

By removing excess water from the soil profile more efficiently, a well-designed drainage system can help greens recover more quickly after periods of heavy rainfall. In turn, this supports firmer surfaces. It also creates more consistent playing conditions.

Improved drainage can also encourage stronger root development. Furthermore, it can give greenkeeping teams greater control over the performance of their putting surfaces throughout the season.

For clubs dealing with persistent wet areas or greens that struggle to drain naturally, a targeted primary drainage system can provide an effective long-term solution.

Continuing Our Work at Effingham Golf Club

The second phase at Effingham builds on an established working relationship between the club and Premier Turfing.

Returning to continue a phased drainage programme allows each stage to be planned around the club’s wider maintenance programme and playing calendar. At the same time, it maintains consistency in the design and installation of the system.